Fairview's three new welcome signs have a contract price of $163,692, and every commissioner who voted on them voted yes. That answers a question being asked in a local Facebook group: who voted to approve the signs, and who voted no. The city's minutes show nobody voted no.
The records point to bond money, not a grant. City officials described it as bond money that had to be spent by a deadline, though the city's latest finance report raises questions about how the signs are being paid for. They leave some questions open, including why the city is now looking at a $4,500 proposal to redo the letters on the signs. The Fairviewian asked City Hall about them on Oct. 17 and has not heard back yet; this story will be updated when it does. This is what the public record shows, including what commissioners said in the recorded meetings.
Who voted
Two votes put the signs in motion, and both were unanimous.
The first was on the design. Resolution 39-25 first came before the board on Aug. 7, 2025. Commissioner Don Bufalini moved to approve it and Commissioner Carolyn Roberts seconded, but Vice Mayor Chris McDonald moved to put it off to the Sept. 4 meeting, with Bufalini seconding, and that carried 5-0. In between, the city let residents vote on three designs. Its count sheet shows 84 valid ballots: Concept A got 32, Concept B 19 and Concept C 33. Fifteen ballots were thrown out, 12 of them from people who did not live in the city.
On Sept. 4, 2025, the board accepted Concept C 5-0, on a motion by Mayor Lisa Anderson and a second by Roberts.
The second vote was on the price. The city opened bids on Feb. 9, 2026, and received one on time, from Jarvis Signs of Madison, Tennessee, which signs its contracts as Jarvis Award, Sign and Flag Co. On Feb. 19, 2026, the board passed Resolution 07-26, accepting the bid at $163,692, on a motion by Roberts and a second by McDonald. It passed 5-0. The minutes list all five members present: Anderson, McDonald, Commissioner Wayne Hall, Roberts and Bufalini.
At that meeting, City Manager Tom Daugherty told the board the bid was under budget and that the city could move some money around. McDonald said a second bid arrived after the deadline and was substantially over, according to the meeting recording.