With construction along Fairview Boulevard that began in September 2025, it's natural to wonder whether the road is finally being widened.
It isn't, and there's no date for when it will be. In May 2024, the Tennessee Department of Transportation told city leaders that widening Hwy 100 from Bowie Lake Road to Interstate 840 is not currently funded in its 10-year plan.
What TDOT said
TDOT officials laid out the state's plans at a May 2, 2024 work session with the Board of Commissioners. Shaun Armstrong of TDOT said the widening "is a wide scale project and not currently funded in the ten year plan at this time," according to the minutes.
Asked about the cost, TDOT's Jay Norris put it at "roughly 80 million dollars." He said the widening is an IMPROVE Act project, one of the projects written into state law along with a gas tax increase, and that TDOT is required by law to complete them. He said the project will be done, but not in the next 10 years, and that TDOT doesn't have enough money to fund all of its projects.
The city had expected sooner. Its 2019 comprehensive plan said the widening would "advance to construction over the next 5 to 10 years."
Cities can partner with TDOT to help pay for projects, and Norris said the state had partnered with 10 cities in its last round. He said some communities had offered $10 million and their projects still did not make the list, while Mt. Juliet put in $25 million and its project did. At an Aug. 20, 2026 meeting, commissioners discussed TDOT's funding requirements and possible city contributions to future projects, and City Manager Bob Rial said the city was starting talks with regional planning groups about getting Fairview into TDOT's statewide plan.
The sidewalk project
The construction on the road since September 2025 is TDOT's Fairview Boulevard improvements. It adds curb and gutter, storm drains and 5-foot sidewalks from the Fairview Community Center to Bowie Lake Road, plus left-turn lanes, a new traffic signal and school-zone flashers at Crow Cut Road and Cumberland Drive.
A city summary from February 2026 lists the funding as TDOT's federal STP funds combined with a multimodal sidewalk grant, $6,987,981, and says the project is 100 percent state and federally funded. Armstrong told the board in 2024 that the sidewalks are being placed so the road can later become three lanes with as little tear-out as possible.
Construction started in September 2025. It was originally scheduled to finish by Aug. 31, 2026, TDOT representatives told commissioners on Sept. 17, 2026. As of Nov. 8, 2026, TDOT's project page still listed the work as under construction, with substantial completion by the end of October 2026 and the crosswalk and permanent signal at Crow Cut Road and Cumberland Drive by the end of November, and noted those dates were subject to change. TDOT's September newsletter said delivery of the permanent signal poles had been delayed. At the September meeting, TDOT said it and the contractor were still working through a time extension. Our earlier story explains .